All of the laminated arches are done and their final joinery work is
near completion. The crew is trial fitting the dormers and lower arch
supports for the hammer beams and making adjustments as required. Detailing
the arch sections and hammer beams continues. The final stain has been
approved and will arrive at the shop tomorrow.